The Timeline

Swimlanes by schedule health, and exactly how a task lands in each one.


The Timeline answers *how is this going?* Teams run down the left, months across the top, and every task sits in a lane that says how its schedule is holding up.

The four lanes

LaneMeans
Ahead of ScheduleMeaningfully further along than the time spent would suggest — or finished.
In ProgressOn pace, or nothing to pace it against yet.
DelayedIts deadline has passed, or its owner told us it has already slipped.
At RiskBehind pace, blocked, flagged in a meeting, or reported at risk.
Lanes are not board columns

Nothing here reads your column names. Two tasks sitting in the same "In progress" column routinely land in different lanes, because the lane is about schedule health, not workflow stage.

How a lane is decided

Noots compares how much of the task's checklist is done against how much of its runway has been spent. The runway ends at the nearest promise the task has made — first match wins:

  1. 1The task's next incomplete milestone.
  2. 2The task's own due date.
  3. 3The Noot's next milestone.
  4. 4The Noot's target date.

If the deadline is a milestone with its own checklist, that milestone's checklist is what gets measured. Then, highest wins:

SignalResult
You dragged the bar into a laneIt stays pinned there until you clear the pin.
The task is doneAhead of Schedule.
The deadline has passedDelayed — a fact outranks an opinion.
A fresh check-in answerWhatever the owner said (see Check-ins).
Blocked, or flagged in a meetingAt Risk.
More than 15 points behind paceAt Risk — and it offers to ask the owner.
More than 10 points ahead of paceAhead of Schedule.
Anything elseIn Progress.

Nothing is graded until 20% of its runway has been spent, so a three-month task doesn't look doomed on day one. Every bar explains itself — hover it and you get the sentence, the deadline it's measured against and the checklist count.

A task with no checklist isn't graded

It sits in In Progress and says so: "No checklist to pace against — add one and this task will track itself against its next milestone." The only other signal available would be the board column, which is exactly what this design rules out.

Working in the Timeline

  • Drag a bar to reschedule it; drag its right edge to change the due date.
  • Drag it into another lane to pin it there by hand.
  • Focus a bar and press / to nudge a day, Shift for a week.
  • Bars fill with checklist completion, so progress is legible without opening anything.
  • Toolbar: Teams groups the chart by team, Completed shows finished work, Lanes renames, recolours, adds or removes swimlanes.
Tip

Renaming a default lane keeps its automatic behaviour — call "At Risk" whatever your team calls it and placement still works. Lanes you add yourself are filled by hand only.